| ECONOMIC JUSTIFICATION OF SEALCOATINGS |
| IT HAS BEEN THE CONSENSUS OF THE INDUSTRY AND PROPERTY OWNERS THAT SEALCOATING WILL SAVE REAL DOLLARS. |
| AS SHOWN IN THE FOLLOWING TABULATION, THE COST SAVINGS WILL BE SUBSTANTIAL, IF THE PAVEMENT IS MAINTAINED ACCORDING |
| TO STAR's RECOMMENDATIONS. I.E. SEALCOATING EVERY 3 YEARS. UNSEALED PAVEMENTS WILL REQUIRE REPAIRS STARTING WITH |
| SECOND YEAR AND AN INCH OF OVERLAY EVERY 7TH. YEAR. |
| ECONOMICS OF SEALCOATING |
| YEAR |
| MAINTENANCE PERFORMED |
| CTPE/ SQ YD. |
| UN-MAINTAINED |
| YEAR |
| Sealed |
| Unsealed |
| 2006 |
| BASE+ 2" ASPHALT |
| $ 19.00 |
| $ 19.00 |
| 2006 |
| 19.60 |
| 19.00 |
| 2 SEALCOATS |
| $ 0.60 |
| 2007 |
| 19.60 |
| 19.18 |
| 2007 |
| 1ST. YEAR MAINTENANCE COST |
| $ - |
| $ 0.18 |
| 2008 |
| 19.60 |
| 19.54 |
| 2008 |
| 2ND.YEAR MAINTENANCE COST |
| $ - |
| $ 0.36 |
| 2009 |
| 20.50 |
| 20.00 |
| 2009 |
| 3RD. YR.MAINTENANCE COST+ 2 SEALCOATS |
| $ 0.25 |
| $ 0.46 |
| 2010 |
| 20.50 |
| 20.75 |
| + 2 SEALCOATS |
| $ 0.65 |
| $ - |
| 2011 |
| 20.50 |
| 21.70 |
| 2010 |
| 4TH. YEAR MAINTENANCE COST |
| $ - |
| $ 0.75 |
| 2012 |
| 21.55 |
| 22.79 |
| 2011 |
| 5TH.YEAR MAINTENANCE COST |
| $ - |
| $ 0.95 |
| 2013 |
| 21.55 |
| 37.29 |
| 2012 |
| 6TH. YEAR MAINTENANCE COST |
| $ 0.35 |
| $ 1.09 |
| 2014 |
| 21.55 |
| 37.64 |
| + 2 SEALCOATS |
| $ 0.70 |
| 2015 |
| 22.75 |
| 38.31 |
| 2013 |
| 7TH.YEAR MAINTENANCE COST |
| $ - |
| $ - |
| 2016 |
| 22.75 |
| 39.76 |
| 1.5 INCH OVERLAY |
| $ 14.50 |
| 2017 |
| 22.75 |
| 41.48 |
| (INCLUDES MILLING @ $1.5/SQ.YD.) |
| 2018 |
| 24.12 |
| 43.98 |
| 2014 |
| 8TH. YEAR MAINTENANCE COST |
| $ - |
| $ 0.35 |
| 2019 |
| 24.12 |
| 47.28 |
| 2015 |
| 9TH. YEAR MAINTENANCE COST |
| $ 0.45 |
| $ 0.67 |
| 2020 |
| 24.12 |
| 51.10 |
| + 2 SEALCOATS |
| $ 0.75 |
| $ - |
| 2021 |
| 25.07 |
| 70.30 |
| 2016 |
| 10TH.YEAR MAINTENANCE COST |
| $ - |
| $ 1.45 |
| 2017 |
| 11TH. YEAR MAINTENANCE COST |
| $ - |
| $ 1.72 |
| 2018 |
| 12TH. YEAR MAINTENANCE COST |
| $ 0.52 |
| $ 2.50 |
| + 2 SEALCOATS |
| $ 0.85 |
| $ - |
| 2019 |
| 13TH.YEAR MAINTENANCE COST |
| $ - |
| $ 3.30 |
| 2020 |
| 14TH. YEAR MAINTENANCE COST |
| $ - |
| $ 3.82 |
| 2021 |
| 15TH.YEAR MAINTENANCE COST |
| $ - |
| $ - |
| 1.5 INCH OVERLAY+ 2 COATS OF SEALER |
| $ - |
| $ 19.20 |
| (INCLUDES MILLING @ $2.5/SQ.YD.) |
| $ 0.95 |
| $ - |
| TOTAL INSTALLATION & MAINTENANCE COST |
| PER SQUARE YARD |
| $ 25.07 |
| $ 70.30 |
| FOR AN AVERAGE PARKING LOT OF 10,000 SQ. YARD |
| $ 250,700.00 |
| $ 703,000.00 |
| SAVINGS - FOR AN AVERAGE PARKING LOT OF 10,000 SQ. YD. |
| $ 452,300.00 |